Database Architecture Review Method

Learn Database Design and Architect - Part 070

Metode review arsitektur database production-grade: review scope, evidence, invariants, workload, consistency, operations, security, failure modes, decision record, dan risk scoring.

16 min read3142 words
PrevNext
Lesson 7084 lesson track70–84 Final Stretch
#database#architecture-review#design-review#risk-management+2 more

Part 070 — Database Architecture Review Method

Database architecture review bukan meeting untuk mencari siapa yang paling senior atau siapa yang paling kuat opininya.

Architecture review adalah proses untuk menjawab:

Given the business process, workload, invariants, failure modes, and operational constraints, is this database design safe enough to run and evolve in production?

Review yang buruk biasanya seperti ini:

  • terlalu fokus pada diagram;
  • terlalu cepat membahas teknologi;
  • tidak memeriksa invariant;
  • tidak memeriksa query shape;
  • tidak memeriksa migration path;
  • tidak memeriksa failure mode;
  • tidak memeriksa operational ownership;
  • tidak menyimpan decision record;
  • approval berdasarkan “looks fine”.

Review yang baik menghasilkan:

  • keputusan yang bisa dijelaskan;
  • risiko yang eksplisit;
  • tradeoff yang diterima secara sadar;
  • checklist action yang jelas;
  • evidence, bukan asumsi;
  • ownership dan revisit trigger.

Bagian ini memberi metode review yang bisa dipakai sebagai internal engineering handbook untuk database design dan architecture review.


1. Review Is a Risk Reduction System

Tujuan review bukan membuat desain sempurna. Tujuan review adalah mengurangi risiko yang paling mahal sebelum desain masuk produksi.

Risiko database biasanya mahal karena:

  • data sulit diperbaiki setelah rusak;
  • migration sulit rollback;
  • schema buruk memengaruhi banyak aplikasi;
  • query buruk bisa menjatuhkan database utama;
  • security leak di database berdampak luas;
  • backup/restore yang belum diuji baru gagal saat krisis;
  • report resmi yang salah bisa menjadi risiko hukum/regulasi.

Jadi review harus diarahkan ke risiko, bukan preferensi.


2. The Review Funnel

Gunakan funnel berikut.

Kalau review langsung lompat ke “pakai Postgres atau MongoDB?”, review sudah salah urutan.

Technology choice datang setelah:

  • data authority jelas;
  • access pattern jelas;
  • consistency requirement jelas;
  • failure mode jelas;
  • operational team mampu menjalankan.

3. Review Inputs

Sebelum review, minta dokumen/artefak minimal.

3.1 Context

  • business capability;
  • user journey/workflow;
  • decision yang bergantung pada data;
  • regulatory/compliance requirement;
  • tenant/security model;
  • integration boundary.

3.2 Data Model

  • conceptual model;
  • logical ERD;
  • physical schema draft;
  • key strategy;
  • relationship cardinality;
  • state machine/lifecycle;
  • reference/master data dependency.

3.3 Workload

  • main write commands;
  • main read queries;
  • reporting/export workload;
  • expected data volume;
  • concurrency;
  • latency target;
  • growth model;
  • multi-tenant distribution.

3.4 Correctness

  • invariants;
  • constraints;
  • transaction boundary;
  • isolation level assumptions;
  • idempotency strategy;
  • dedup/retry design;
  • correction/repair path.

3.5 Operations

  • migration plan;
  • backup/restore plan;
  • observability plan;
  • runbook draft;
  • capacity estimate;
  • failure-mode analysis.

If there is no evidence, mark it as assumption. Do not allow assumptions to masquerade as facts.


4. Review Output

Architecture review harus menghasilkan output konkret:

  1. Decision: approve, approve with conditions, needs redesign, or reject.
  2. Risk register: risk, impact, likelihood, mitigation, owner.
  3. Action items: specific, assigned, due.
  4. Decision record: context, options, tradeoffs, chosen approach.
  5. Revisit triggers: when this design must be reviewed again.

Contoh status:

StatusMeaning
Approveddesain siap dengan risiko acceptable
Approved with conditionsboleh lanjut setelah action tertentu selesai
Needs redesigndesain punya flaw struktural
Spike requiredevidence belum cukup, perlu experiment/benchmark/prototype
Rejectedrisiko tidak acceptable untuk production

5. Phase 1 — Business and Data Authority Review

Pertanyaan inti:

  • data ini mewakili real-world entity apa?
  • siapa owner data?
  • siapa boleh membuat/mengubah/menghapus?
  • sistem mana source of truth?
  • apakah ada derived copy?
  • apakah ada external authority?
  • apakah correction boleh dilakukan?
  • apakah data menjadi evidence?

Smells

SmellWhy Dangerous
“This table is shared by many services”ownership kabur
“Both systems can update this field”conflict authority
“We sync both ways”correctness sulit dibuktikan
“Report uses whichever value is latest”semantic ambiguity
“Admin can edit anything”audit/correction boundary lemah

Review Questions

  • Apakah setiap table punya owning capability/team?
  • Apakah setiap mutable field punya authority?
  • Apakah source of truth dan projection dibedakan?
  • Apakah correction path diaudit?
  • Apakah deletion/retention dipahami?

Evidence

  • data ownership matrix;
  • system-of-record diagram;
  • lifecycle diagram;
  • integration contract;
  • audit/correction requirement.

6. Phase 2 — Invariants Review

Database design harus dimulai dari state yang tidak boleh terjadi.

Contoh invariant:

  • satu case hanya boleh punya satu active assignment;
  • tenant A tidak boleh melihat data tenant B;
  • closed case tidak boleh diedit kecuali lewat reopen transition;
  • ledger entry tidak boleh diubah setelah posted;
  • effective-dated rule tidak boleh overlap;
  • idempotency key hanya boleh menghasilkan satu business result;
  • deleted entity tidak boleh muncul di search/export.

Invariant Table

InvariantEnforcementFailure ImpactTest
One active assignment per casepartial unique indexduplicate work, SLA wrongconcurrent assignment test
Valid state transition onlytransition table + transactionillegal workflowtransition matrix test
Tenant isolationtenant_id + RLS + testsdata breachcross-tenant query test
No overlapping effective periodexclusion constraint/app lockwrong rule selectionoverlap insert test

Review Questions

  • Apakah invariant ditulis eksplisit?
  • Mana yang ditegakkan database?
  • Mana yang ditegakkan aplikasi?
  • Mana yang butuh transaksi?
  • Mana yang rentan race condition?
  • Apakah ada concurrent test?
  • Apakah invariant monitoring ada?

Strong Signal

Desain yang matang bisa menjawab:

“Here are the illegal states, and here is exactly where each illegal state is prevented, detected, or repaired.”


7. Phase 3 — Workload Review

Schema yang tampak bersih bisa gagal jika workload-nya salah dipahami.

Review workload dengan format command/query.

Write Workload

CommandFrequencyRows touchedTransaction boundaryContention risk
Create casehighcase + audit + outboxsingle txnunique case number
Assign casemediumcase + assignment + transitionsingle txnactive assignment invariant
Close casemediumcase + decision + auditsingle txnstatus transition
Import evidenceburstyevidence + file metadatamulti-stepstorage side effect

Read Workload

QueryFrequencyFreshnessExpected RowsIndex
My active taskshighcurrent20–100tenant, assignee, status
Case timelinemediumcurrent100–1000case_id, occurred_at
SLA dashboardhigh<=5 min staleaggregateprojection/aggregate
Monthly reportlowsnapshotmillionswarehouse/snapshot

Review Questions

  • Apakah query shape diketahui?
  • Apakah setiap high-frequency query punya index strategy?
  • Apakah write amplification dari index diterima?
  • Apakah reporting workload diisolasi?
  • Apakah hot row/key/tenant dianalisis?
  • Apakah pagination bounded?
  • Apakah parameter bebas dibatasi?

Required Evidence

  • top N query list;
  • expected volume;
  • expected concurrency;
  • EXPLAIN untuk query kritis jika schema/data sudah ada;
  • load test plan untuk workload berisiko.

8. Phase 4 — Schema Review

Schema review memeriksa apakah model logis benar-benar menjadi physical schema yang aman.

Table Review

  • Apakah table punya grain jelas?
  • Apakah table terlalu banyak tanggung jawab?
  • Apakah nullable columns punya alasan?
  • Apakah status enum mencampur beberapa state machine?
  • Apakah history/current state dipisahkan dengan benar?
  • Apakah relationship-as-entity digunakan ketika relationship punya lifecycle?

Key Review

  • Primary key stabil?
  • Natural key perlu unique constraint?
  • Public identifier terpisah dari internal identifier?
  • Composite key digunakan dengan sadar?
  • Tenant-scoped uniqueness jelas?
  • Foreign key dipakai ketika boundary memungkinkan?

Constraint Review

  • NOT NULL untuk mandatory fields?
  • CHECK untuk domain sederhana?
  • UNIQUE untuk business uniqueness?
  • partial unique untuk active/current constraints?
  • FK untuk referential integrity?
  • exclusion constraint untuk interval overlap?
  • generated column untuk derived invariant sederhana?

Index Review

  • Index sesuai query shape?
  • Composite index order tepat?
  • Partial index digunakan untuk subset dominan?
  • Covering index perlu atau tidak?
  • Redundant indexes dibuang?
  • Write amplification dihitung?
  • FK columns yang sering join/delete punya index?

Smells

SmellRisk
status with 30 valueshidden state machines
metadata_json stores core fieldsconstraint/query/reporting weak
nullable everythinginvalid state easy
no FK because “microservices”orphan data inside same boundary
EAV for normal domain attributesweak type, weak constraint, bad query
polymorphic FKreferential integrity lost
audit table without actor/reasonweak evidence

9. Phase 5 — Transaction and Consistency Review

Pertanyaan inti:

  • operasi mana harus atomic?
  • invariant mana lintas row/table?
  • apakah isolation level cukup?
  • apakah write skew mungkin?
  • apakah retry safe?
  • apakah external side effect dipisah dari DB transaction?

Transaction Boundary Template

Command: Assign Case
Atomic changes:
- create assignment row
- mark previous assignment inactive
- insert case_transition
- insert audit_event
- insert outbox_event

Consistency requirements:
- only one active assignment per case
- assignee must belong to tenant/unit
- case must be assignable state

Concurrency strategy:
- transaction
- lock case row or active assignment row
- partial unique index on active assignment
- retry on serialization/deadlock

Review Questions

  • Apakah read-modify-write aman?
  • Apakah lost update dicegah?
  • Apakah write skew dicegah?
  • Apakah retry policy tahu error mana yang retryable?
  • Apakah idempotency key tersedia untuk command eksternal?
  • Apakah outbox digunakan untuk event publish?
  • Apakah commit-unknown ditangani?

10. Phase 6 — Evolution and Migration Review

Database design yang bagus tapi tidak bisa dimigrasikan adalah desain yang belum selesai.

Review Questions

  • Apakah schema change backward compatible?
  • Apakah expand–migrate–contract plan tersedia?
  • Apakah backfill online dan resumable?
  • Apakah DDL lock impact dipahami?
  • Apakah rollback/roll-forward plan jelas?
  • Apakah validation query tersedia?
  • Apakah dual read/write perlu?
  • Apakah old app dan new app bisa berjalan bersamaan?

Migration Risk Classification

RiskExampleReview Demand
Lowadd nullable columnnormal review
Mediumadd index concurrentlymonitor lock/WAL/load
Highbackfill billion rowsbatch plan + validation + rollback
Criticalchange primary key/shard keyredesign/spike required
Criticalsplit table used by many servicescompatibility plan + consumer coordination

11. Phase 7 — Security and Privacy Review

Security review harus masuk ke database design, bukan ditempel di akhir.

Review Questions

  • Apakah tenant boundary enforced?
  • Apakah least privilege role design tersedia?
  • Apakah aplikasi memakai owner role atau limited role?
  • Apakah RLS diperlukan?
  • Apakah sensitive columns diidentifikasi?
  • Apakah export/report masking diterapkan?
  • Apakah backup encrypted dan access-controlled?
  • Apakah CDC/search/warehouse menerima PII?
  • Apakah break-glass access diaudit?
  • Apakah retention/erasure/legal hold jelas?

Evidence

  • data classification matrix;
  • role/privilege matrix;
  • RLS/access policy tests;
  • audit event schema;
  • privacy propagation diagram;
  • backup/restore access policy.

12. Phase 8 — Operational Readiness Review

Production database bukan hanya schema. Ia perlu operasi.

Observability

  • slow query visibility;
  • query fingerprint;
  • lock wait visibility;
  • connection pool metrics;
  • replication lag;
  • WAL growth;
  • disk usage;
  • cache hit ratio;
  • autovacuum/bloat signal;
  • migration progress;
  • report/export queue;
  • CDC/outbox lag.

Backup and Restore

  • RPO/RTO jelas;
  • PITR tersedia jika perlu;
  • restore drill dilakukan;
  • restore validation query tersedia;
  • tenant-level restore strategy jelas;
  • backup retention sesuai compliance;
  • backup access diaudit.

Runbook

  • slow query storm;
  • lock storm;
  • connection exhaustion;
  • disk full/WAL pressure;
  • replication lag;
  • bad migration;
  • failed backup;
  • data correctness incident;
  • security incident.

Review Questions

  • Siapa owner saat incident?
  • Alert apa yang actionable?
  • Apa degraded mode?
  • Apa manual mitigation?
  • Apa recovery proof?
  • Apa post-incident data validation?

13. Phase 9 — Failure Mode Review

Gunakan failure-mode table.

Failure ModeCauseDetectionMitigationRecoveryOwner
Duplicate active assignmentrace conditioninvariant monitorpartial unique + transactionrepair duplicatecase platform
Report wrong after schema changeunversioned metricreconciliation failmetric versioningregenerate official report with auditanalytics
Tenant data leak in exportmissing scope predicateaccess audit anomalyreport access scoperevoke artifact, incident responsesecurity
Backfill overloads primaryunthrottled updateCPU/WAL/lag alertbatch + throttlepause/resumeplatform
Replica stale read breaks workflowread routed to replicastate mismatchprimary read for command guardsretry from primaryapplication

Review Questions

  • Apa top 10 failure modes?
  • Mana yang catastrophic?
  • Mana yang likely?
  • Mana yang tidak bisa dideteksi cepat?
  • Mana yang recovery-nya belum terbukti?
  • Mana yang perlu redesign, bukan runbook?

14. Scoring Model

Gunakan scoring sederhana. Jangan pura-pura terlalu presisi.

Risk Score

Risk Score = Impact x Likelihood x Detectability

Skala 1–5:

Dimension15
Impactminor inconveniencedata loss/breach/outage/regulatory failure
Likelihoodrarelikely under normal production load
Detectabilityobvious immediatelysilent for days/months

Interpretasi:

ScoreMeaning
1–20acceptable with normal controls
21–50mitigation required
51–80senior review required
81–125redesign or explicit executive risk acceptance

Detectability penting. Silent corruption lebih berbahaya daripada failure yang langsung terlihat.


15. Architecture Decision Record for Database

Template ADR:

# ADR: <Decision Title>

## Status
Proposed | Accepted | Superseded | Rejected

## Context
What business process, data, workload, and constraints drive this decision?

## Decision
What are we choosing?

## Options Considered
1. Option A
2. Option B
3. Option C

## Tradeoffs
What do we gain and lose?

## Invariants Protected
Which illegal states does this design prevent?

## Consistency Model
What is strongly consistent, eventually consistent, stale-allowed, or async?

## Migration Plan
How will this be introduced without downtime/data loss?

## Failure Modes
What can go wrong and how do we detect/recover?

## Operational Requirements
Monitoring, backup, restore, runbook, capacity, ownership.

## Security and Privacy
Access control, sensitive data, audit, retention.

## Revisit Triggers
When should this decision be reviewed again?

Good ADRs are not essays. They are decision evidence.


16. Example Review — Case Assignment Design

Proposal

A case can be assigned to an officer. Current assignment is stored in case.assigned_user_id. Assignment history is stored in case_assignment_history.

Review Finding

Potential flaw:

  • current state and history can drift;
  • no invariant preventing multiple active assignments if future design adds active assignment table;
  • reassignment reason not mandatory;
  • concurrency behavior unclear;
  • assignment authorization not represented;
  • SLA impact not defined.

Improved Design

create table case_assignment (
    case_assignment_id uuid primary key,
    tenant_id uuid not null,
    case_id uuid not null,
    assigned_user_id uuid not null,
    assigned_by uuid not null,
    assigned_at timestamptz not null,
    unassigned_at timestamptz,
    assignment_reason text not null,
    is_active boolean generated always as (unassigned_at is null) stored
);

create unique index case_assignment_one_active_uq
on case_assignment (tenant_id, case_id)
where unassigned_at is null;

Transaction:

begin;

select *
from enforcement_case
where tenant_id = :tenant_id
  and case_id = :case_id
for update;

update case_assignment
set unassigned_at = now()
where tenant_id = :tenant_id
  and case_id = :case_id
  and unassigned_at is null;

insert into case_assignment (
    case_assignment_id,
    tenant_id,
    case_id,
    assigned_user_id,
    assigned_by,
    assigned_at,
    assignment_reason
)
values (
    gen_random_uuid(),
    :tenant_id,
    :case_id,
    :assigned_user_id,
    :assigned_by,
    now(),
    :reason
);

insert into case_transition (...);
insert into audit_event (...);
insert into outbox_event (...);

commit;

Review conclusion:

  • approve with condition: add concurrent assignment test, authorization check, SLA impact rule, and migration path from existing assigned column.

17. Review Meeting Format

Keep it structured.

Before Meeting

  • reviewer reads design doc;
  • author identifies top risks;
  • data volume and workload assumptions included;
  • open questions listed.

During Meeting

  1. context and scope;
  2. data ownership;
  3. invariants;
  4. workload;
  5. schema/transaction design;
  6. migration plan;
  7. security/privacy;
  8. operations/failure modes;
  9. decision and actions.

After Meeting

  • publish decision record;
  • track action items;
  • schedule follow-up if conditional approval;
  • update standard/checklist if new pattern discovered.

18. Review Anti-Patterns

Anti-PatternWhy It Fails
Review by senior tasteinconsistent, political
Diagram-only reviewignores invariants/workload
Technology-first reviewmisses domain constraints
No written assumptionsdecisions become folklore
No failure-mode reviewproduction discovers design flaws
No migration reviewgood schema cannot be deployed safely
No ownership reviewshared database becomes unmanaged
No revisit triggerdesign remains after assumptions expire
Approval without conditionsaction items disappear

19. Revisit Triggers

A design must be reviewed again when:

  • data volume grows 10x;
  • QPS/TPS grows 3x;
  • tenant count or largest tenant grows significantly;
  • report/export workload changes;
  • new regulatory/privacy requirement appears;
  • schema ownership changes;
  • service boundary changes;
  • a new database engine is introduced;
  • backup/restore objective changes;
  • incident reveals hidden failure mode;
  • latency SLO changes;
  • new region/data residency requirement appears.

Architecture decisions expire when assumptions expire.


20. Database Architecture Review Checklist

Context

  • Business capability clear.
  • Data owner clear.
  • Source of truth clear.
  • Derived/projection stores identified.
  • Regulatory/compliance context captured.

Data Model

  • Conceptual/logical/physical model aligned.
  • Table grain clear.
  • Key strategy clear.
  • Relationship cardinality clear.
  • Lifecycle/state machine clear.
  • Temporal semantics clear.

Correctness

  • Invariants documented.
  • Enforcement layer identified.
  • Database constraints used where appropriate.
  • Concurrency risks tested.
  • Idempotency/retry strategy clear.
  • Correction/repair path clear.

Workload

  • Critical commands listed.
  • Critical queries listed.
  • Reporting/export workload isolated.
  • Index strategy reviewed.
  • Hotspot/skew analyzed.
  • Capacity estimate exists.

Consistency

  • Transaction boundaries clear.
  • Isolation assumptions clear.
  • Replica/stale-read behavior clear.
  • Event/CDC ordering clear.
  • Distributed consistency tradeoff documented.

Migration

  • Expand–migrate–contract plan.
  • Online backfill plan.
  • Validation plan.
  • Rollback/roll-forward plan.
  • Old/new app compatibility checked.

Security and Privacy

  • Least privilege roles.
  • Tenant isolation.
  • RLS/ABAC/ACL decision clear.
  • Sensitive fields classified.
  • Audit events defined.
  • Retention/erasure/legal hold defined.

Operations

  • Monitoring dashboard.
  • Alert strategy.
  • Backup/restore tested.
  • Runbook exists.
  • Failure modes reviewed.
  • Ownership and escalation clear.

Decision

  • Options compared.
  • Tradeoffs explicit.
  • Risks scored.
  • Action items assigned.
  • Revisit triggers defined.
  • ADR published.

21. Key Takeaways

Database architecture review is a discipline of making hidden assumptions visible.

A strong review asks:

  • What is the source of truth?
  • What states are illegal?
  • What workload will hit this design?
  • What consistency does each operation need?
  • What happens during concurrency?
  • How will this change safely?
  • How will this fail?
  • How will we know it failed?
  • How will we recover?
  • Who owns the result?

The goal is not to block engineering velocity. The goal is to prevent irreversible data mistakes, fragile migrations, expensive outages, silent report errors, and security failures.

A top-level database architect does not win reviews with opinions. They win by making tradeoffs explicit, risks measurable, and decisions defensible.


References

  • AWS Well-Architected Framework — Operational Excellence, Reliability, Security, Performance Efficiency, Cost Optimization
  • PostgreSQL Documentation — constraints, indexes, transactions, locking, monitoring, backup/recovery
  • NIST security/privacy control and risk management concepts
  • Prior parts in this series: Part 001–069
Lesson Recap